Nesconset Renovation Moving Along at a Good Pace!

The interior walls are taking shape in the future Main Room. The hole cut in the wall is for a window that will add more natural light to the building.

A birds-eye view! The roof nears completion and the metal trim work has been attached to the new facade. The framework for the skylights is in place, and once completed, will allow more natural light into the building. The large stacks shown are roofing material that is being installed.

A view taken towards Smithtown Blvd. shows the installation of the water main to the building.



Steel and Stone Work at Commack



Steel and stone work nears completion at the Commack Branch. The future main entrance is located straight ahead while the new Children's Department is to the right.

The floor has been cut for the future installation of the elevator.